39 storage and retrieval machines are being replaced by 61 new ones in a high-bay warehouse with 1.2 million storage locations that cannot be shut down. The Stöcklin Group is carrying out this project as the general contractor at Hermes Fulfilment in Haldensleben.
Each new stacker crane weighs about 12 metric tons. The masts are 27 meters high. Installing them poses a unique logistical challenge: A heavy-duty crane lifts the masts and the rack feeders over the warehouse and lowers them through a roof opening that is only a few centimeters wider than the rack feeder or the mast itself.
Even a gust of wind can jeopardize the operation. The 39 old units leave the warehouse through the same roof openings.
The warehouse is over 90 percent occupied and operates on a six-day workweek, including during seasonal e-commerce peaks. More than 120 million items are shipped annually from Haldensleben to over 20 European countries. An interruption is therefore not an option.
Old and new technology will run in parallel until the project is completed, step by step, across nine construction phases through the end of 2028. The result will be greater performance, greater precision, and greater resilience: throughput will increase from around 3,500 to up to 3,900 storage and retrieval operations per hour.
For Hermes Fulfilment, it’s clear why a custom solution is needed. “A standard, off-the-shelf solution simply won’t work here,” says Claas Matthaeas, Senior Project Manager for Logistics Planning and Consulting at Hermes Fulfilment.
Read the full story in the Issue 11-12/2026 of materialfluss.